MRP logic: gross requirements to order releases
The question it answers
Once the master production schedule is set, how many components at each level should an operations manager order or make, and when, to avoid shortages?
- Origin
- Slack et al. (2022)
- Diagram type
- Process by phase
- Level of analysis
- Firm

Diagram
MRP logic: gross requirements to order releases
- Inputs
- Bill of materials
- MPS
- Inventory records
- Calculate level by level
- Gross requirements
- Net off projected stock and scheduled receipts to get net requirements
- Round to lot size
- Offset by lead time into order releases
- Repeat at the next BOM level